Heathrow Airport – Taxiway Reconstruction
Sector: Aviation
Client: Morgan Sindall
Main Contractor: Morgan Sindall
Project: Heathrow Airport – Taxiway Reconstruction
Works:
Scheme 22 works
- 56no PQ Concrete Bay Replacements
- Repairs to existing Wet lean layer
- Local concrete repairs
N6 RET Works
- Grade and compact type sub base
- Install profiled formwork
- Place steel reinforcement
- Pour new 400mm thick PQ Concrete pavement
- Precast and install new concrete catch pits
- Install new slot channel drainage
TAG Managed their airside access and passes for this scheme. TAG also supplied a variety of labour to Morgan Sindall for other site works throughout the project.